PERFORMANCE INDICATORS OF TRANSMISSION

 

CE (TR)/ACE (TR)/SE/EE/DE-L/991                                                    Date: 11.11.2011

REPORT ON KEY PERFORMANCE INDICATORS OF TRANSMISSION FOR Sept-2011.

 

 

 

 

(A) System Availability: -

 

 

 

Unit

Previous year –this month

Current year – this month

Rating

Remarks

400KV Trans. Lines

%

99.18

99.06

Good

 

220KV Trans. Lines

%

99.46

99.33

Good

 

132KV Trans. Lines

%

99.58

99.36

Excellent

 

66 KV Trans. Lines

%

99.82

99.82

Excellent

 

SUB-STATIONS

%

99.88

99.85

Excellent

 

 

TRANSMISSION SYSTEM AVAILABILITY = 99.43%       (Worked out for 132 KV & above as per CEA guideline)

 




(B) Network Outages and Faults :-

 

Voltage  KV

Unit

Previous year – this month

Current year – this month

Rating

Remarks

Planned Outages

400

Hrs/ 100 km

4.90

1.40

Excellent

 

220

6.03

6.67

Good

 

132

3.41

6.20

Good

 

66

5.30

7.63

Good

 

Transient Trippings

400

Nos/ 100 km

0.00

0.00

Excellent

 

220

0.45

0.36

Good

 

132

0.95

1.31

Good

 

66

1.69

1.16

Good

 

Permanent Faults

400

Nos/ 100 km

0.00

0.00

Excellent

 

220

0.18

0.14

Good

 

132

0.07

0.20

Good

 

66

0.18

0.22

Good

 

ESD

400

Nos/ 100 km

0.14

0.04

Excellent

 

220

0.06

0.10

Good

 

132

0.15

0.10

Good

 

66

0.19

0.15

Good

 

 

 

 

 

 

(C)  Safety : (Employees Accidents only) : -

 

Previous year - this month                            : 0 Nos. of accidents

Current Year – this month                    : 3 Nos. of accidents (1-Fatal & 2-Nonfatal)

Rating                                                : Average

 

Previous year – up to this month                   :  2 Nos. of accidents (2-Nonfatal)

Current Year  – up to this month          :  5 Nos. of accidents (1 Fatal & 4-Nonfatal)

Rating                                                :  Average

 

 

(D)  Equipment Failure: - 

(In percentage and Nos. of total population of each category)

 

Equipment

 

Transformer

CT

PT

LA

CB

Previous year – this month

%

0.09

0.02

0.12

0.07

0.01

Nos

2

4

4

7

2

Current year – this month

%

0.13

0.02

0.11

0.02

0.01

Nos

3

3

4

3

2

Rating

 

Good

Excellent

Good

Excellent

Excellent

 

 

 

 

 

Previous year – till this month total failure

%

0.75

0.62

0.55

0.31

0.05

Nos

17

102

19

33

8

Current year – till this month total failure

%

0.81

0.34

0.34

0.32

0.04

Nos

19

63

13

39

7

The overall cumulative failure of equipment is reduced as compared to last year

 

 

 

(E)   % Availability of Capacitor Banks : -

 

 

132Kv class

66kV class

11kV class

Installed MVAR

216.0

1312.7

2574.8

Available MVAR

216.0

1234.8

2425.3

% availability

100%

94.07%

90.67%

Rating

Excellent

Average

Average

  

(F) Substation Inspection: -

 

 

132kV & above s/s

66kv s/s

Total Nos. of s/s

129

990

Inspected s/s during previous year – this month

14

155

Inspected s/s during current year – this month

21

143

Rating

Good

Excellent

 (G) Bus faults :

 

During previous year – this month

7 Nos.

During current year  – this month

7 Nos.*

Rating

Average

Note: - (*)Bus fault occurred at  (1) 220Kv Dahej s/s of Bharuch circle. (2) 66Kv Solankipura s/s of Nadiad circle (3) 66Kv Khanpur s/s of Mehsana circle (4) 66 Kv Jadiya s/s of Palanpur circle (5) 66kv Umrali s/s and 66Kv Rafaleshwar s/s of Gondal circle (6) 400 Kv Chorania s/s of Chorania circle.

 (H) Transmission Loss :

(Banchmark for the Transmission losses for the year 2011-12 = 4.18%)

 

 

Conventional method

Revised method*

Final Revised Calculation

(After deducting APL-Sami-Dehgam line losses)

Previous year –

this month

4.65 %

4.41 %

4.41 %

Current year –

this month

4.29 %

3.92 %

3.80 %

 

Previous year –

Average up to this month

4.39 %

4.05 %

4.05 %

Current year  -

Average up to this month

4.73 %

4.41 %

4.20 %

Rating

Average

Good

Good

Note: (*) as per the new methodology proposed by ARR.

 

 

Total MUs

Agriculture MUs

% Agriculture MUs

Previous year– this month                          

   4178.28

590.02

14.12

Current year – this month

4300.31

576.79

13.41

 

 

CE (TR)

 

 